The Town of Caledon is studying the following locations to address structural deficiencies, prolong service life, and enhance roadside safety:

Caledon Trailway (2 Locations)

For the replacement of two Caledon Trailway culverts, approximately 0.3 km and 0.15 km north of Isabella Street. 

Creditview Road

For the rehabilitation of Creditview Road bridge, approximately 0.1 km north of Station Road. 

Old School Road

For the rehabilitation of the Old School Road Bridge, approximately 0.8 km west of Airport Road.

Mill Street

For the rehabilitation of the Mill Street bridge, approximately 0.2 km west of Creditview Road.

Caledon Trailway

For the rehabilitation of the Caledon Trailway bridge, approximately 0.37 km south of Olde Baseline Road. 

Boston Mills Road

For the rehabilitation of the Boston Mills Road bridge, approximately 0.02 km west of Chinguacousy Road. 

Humber Lea Road

For the rehabilitation of the Humber Lea Road bridge, approximately 0.02 km north of King Street. 

THE PROCESS:

These projects are Schedule ‘A+’ undertakings under the Municipal Class Environmental Assessment process.  A Public Information Centre (PIC) will be scheduled later this year to present designs and address any questions or concerns. In the meantime, however, if you have any questions or comments about the project, please contact one of the following Project Team Members for more information. 

Ian Todhunter, P.Eng.
Project Manager
Finance and Infrastructure Services
Town of Caledon
6311 Old Church Road
Caledon, ON  L7C 1J6
Tel: 905-584-2272 x4065
E-mail: Ian.Todhunter@caledon.ca

Scott Kerr
Project Manager
The Greer Galloway Group Inc.
Consulting Engineers
1620 Wallbridge Loyalist Rd
Belleville, ON K8N 4Z5
Tel: 613-966-3068 x388
E-mail: skerr@greergalloway.com