Lotus Point
Starting August 2, 2016 there will be road construction throughout the Lotus Point subdivision. Please refer to the construction notice and location map appended below.
The following activities will occur on the roads highlighted in the attached map:
- Lowering of the manholes on the roads. Steel plates will be placed over the manholes as required for vehicular safety.
- The base curb will be fully removed and replaced with full curb for the roads highlighted in red.
- Top curb will be placed for the roads highlighted in orange.
- Grinding of the existing asphalt to granular elevation.
- Raising of the manholes on the roads.
- New base asphalt will be placed on the highlighted roads.
Pending weather delays, these works should take approximately 6 – 8 weeks to complete.
Contact
For more information about this project, please contact Brandon DiLollo, B. Eng., David Schaeffer Engineering Ltd., at 905-475-3080 ext. 259.