Peel Region Public Notice - Resurfacing of The Gore Road
Project 22-4685
Where is the work happening?
- On The Gore Road from Healy Road to King Street, Town of Caledon
What are we doing?
- The work includes:
- removal and replacement of asphalt pavement on The Gore Road;
- removal of granular shoulder and replacement with asphalt shoulder;
- removal and replacement of steel beam guide rails;
- intersection improvements and traffic signal modifications.
When?
- Construction Start: August 2024 - Finish: October 2024 (weather permitting)
Working Hours
- Four Seasons Site Development Ltd. has been contracted to complete the work on the Region’s behalf. Hours of operation are from 6 a.m. to 7 p.m., Monday to Friday and work may also be done on Saturdays.
- These hours follow the city’s by-laws. Extended working hours may cause some inconvenience to the public however will help facilitate completion of the project as quickly as possible.
Traffic Control
- The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.
- Existing traffic flows will be maintained during construction. However, due to the nature of the work, we will need to reduce traffic lanes to a single lane and temporarily block intersection during construction.
- Emergency access will be maintained at all times.
- Please use caution when travelling through the work zone.
Driveway Access
- We will maintain driveway access as much as possible and if we need to block your driveway for a short time you will be contacted to arrange for the best time
- We will make sure businesses have access at all times.
Project Updates
- The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
- Please call the project manager if you have any special needs.
Who can you call?
- Umair Keen, Region of Peel Project Manager at 905-791-7800 ext. 1401