St. Andrews Road Culvert Replacement
Project Name: Culvert #1204 Replacement
St. Andrews Road will undergo a road closure to complete the replacement of structure #1204. The last available emergency access available Northbound from Charleston Side Road is 19275 St Andrews Rd. The last available emergency access available southbound from Beech Grove Side Road is 19250 St Andrews Rd. The designated detour route is Beech Grove Side Rd Horseshoe Hill Rd, and Charleston Side Rd. Please see attached key plan.
Contract No.: Emergency Contract
Project Location: St. Andrews Road Culvert #1204 between Charleston Side Road and Beechgrove Side Road
Contractor: Sierra Excavating Enterprises Inc
Anticipated Commencement Date (Weather permitting): August 15, 2022
Anticipated Completion Date (Weather permitting): September 12, 2022
Contact Persons and Telephone Numbers (during business hours):
Contractor: Sierra Excavating Enterprises Inc
- Office Telephone: 905-951-3337
- Working hours: 7 a.m. - 5 p.m.
- Staff: Dominic Scrivo (Project Manager)
- 905-951-3337 (Cell)
- estimating@sierraexcavating.ca
Consultant: R.J. Burnside and Associates Limited
- Office Telephone: 1-800-265-9662
- Staff: Chris Knechtel (Contract Administrator)
- 519-938-3012 (Cell)
- chris.knechtel@rjburnside.com
Owner: Town of Caledon – Engineering Services Department:
- Service Caledon: 905-584-2272 x 7750
- Office Telephone (after hours): 1-800-563-7881
- Email: info@caledon.ca
- Staff:
- Taylor Bliss (Senior Project Manager), 905-584-2272 x. 4171 (Office)
- Ryan Grodecki (Manager, Engineering), 905-584-2272 x 4101 (Office)